Our panel of surveyors provides a wide range of surveying services to people living in Wimbledon, London and the Home Counties so that they can make well-informed choices about land and property. Your surveyors can undertake a Schedule of Condition for a detailed snapshot of the property condition in respect of party wall agreements. Wimbledon Surveyors can organise RICS valuers for lease agreements and property purchases. Expert chartered surveyors also deliver meticulous building surveys to safeguard your property interests. Surveying services cover residential, commercial, industrial and retail to deliver comprehensive property surveys.
OUR LATEST ARTICLE
Orford Court RTM v Brickfield Properties (FTT, 2026): Fire Doors That Failed the 2019 Standard, £20,640 Re-Credited and a Surveyor’s Fee Cut by Half, Service Charge Dispute Lessons for Wimbledon Flat Owners and Surveyors (November 2026)
New flat entrance doors were fitted in 2019 as part of a major works programme. Six years later, a fire door consultant found they did not meet the fire standards that applied when they were installed. The service charge dispute that followed ended with the door costs being handed back
Elliott v Lloyd’s Syndicate 4444 (2026) EWHC 1773 (TCC): Subsidence Claim on a Grade II Listed House Fails After Monitoring Shows Millimetres of Movement and Rebuild Cost Is Put at £1,615,000, Expert Witness Lessons for Surveyors and Homeowners (November 2026)
A homeowner brought a subsidence claim for about £553,500 plus VAT to underpin a Grade II listed house, saying the damage had happened during a one-year buildings policy. On 15 July 2026 the Technology and Construction Court dismissed the claim in full [1]. The engineering experts could not show that
Harvey v Heaver (2026) EWHC 1671 (KB): ‘Frankly, Deplorable’ Damp, a Single Joint Expert Surveyor Nobody Cross-Examined and a £39,150 Schedule of Works, Housing Disrepair Lessons for Wimbledon Landlords, Tenants and Surveyors (November 2026)
{"content":[]} Moisture readings of 999 on a scale where anything above 200 counts as wet. That was the evidence in Harvey v Heaver (2026) EWHC 1671 (KB), a High Court decision in which a Deputy Judge found a rented family home unfit for human habitation and ordered the landlord to
Groundinvest (101) v Watkinson (2026) UKUT 450 (LC): A 200% Jump in Block Insurance, a Missing Reinstatement Cost Assessment and a Tribunal Finding With No Evidence Behind It, Service Charge Dispute Lessons for Wimbledon Flat Owners and Surveyors (November 2026)
The insurance bill for 251 flats went from £66,529 to £204,024 in a single year after the freehold changed hands. Ninety-nine leaseholders challenged it. On 20 November 2026 the Upper Tribunal (Lands Chamber) gave its decision in Groundinvest (101) Ltd v Watkinson (2026) UKUT 450 (LC) [1]. The result was
Eiger Funding v Ridge (2026) EWHC 609 (TCC): A Monitoring Surveyor, an Undisclosed Conflict and £2.5 Million in Damages, Surveyor Negligence Lessons for Wimbledon Lenders, Developers and Surveyors (November 2026)
A lender advanced £12.9 million on the strength of a monitoring surveyor's report that put the cost to complete a development at about £2.9 million. The court found the realistic figure was closer to £5.4 million, and that the surveyor had previously priced the same project for the developer without
Thirsk v Berkeley Homes (2026) EWHC 215 (TCC): A £1.2m Flat Defects Claim, a Developer’s Costs Budget Cut Back and £140,000 Allowed for Experts, Lessons for Wimbledon Flat Owners and Surveyors (November 2026)
The owners of one London flat are claiming about £1.2m for alleged defects. Their own legal budget to trial has been agreed at more than £1.15m. The developer wanted to spend far more, and the High Court has said no. For anyone in Wimbledon weighing up a building defect claim,
Avon Ground Rents v Li Jing (2026) UKUT 412 (LC): A £203,888 Waking Watch, a Delayed Fire Alarm and How the Upper Tribunal Recalculated What Leaseholders Must Pay, Lessons for Wimbledon Flat Owners and Surveyors (November 2026)
A waking watch that was meant to last six months ran for twelve and cost leaseholders' service charge account £203,888. The fire alarm that would have ended it cost a fraction of that. On 26 October 2026 the Upper Tribunal (Lands Chamber) confirmed that the landlord could not recover the
John Wright Electrical v M B Plant (2026) EWHC 3010 (TCC): A Fire-Stopping Sealant, Leaking Sprinkler Pipes and Why a Letter of Response Was Not an Admission, Building Defect Claim Lessons for Wimbledon Owners and Surveyors (November 2026)
A fire-stopping job quoted at £15,122.80 has produced a High Court judgment. Handed down on 20 November 2026, John Wright Electrical & Mechanical Services Ltd v M B Plant Ltd (trading as 123 Fire) (2026) EWHC 3010 (TCC) is about leaking sprinkler pipes in a York refurbishment, and about whether
Loughton Contracts v Amtico (2026) EWHC 2814 (TCC): £2.9m Failed Flooring Claim Survives Strike-Out Despite Late Particulars, Building Defect Claim Lessons for Wimbledon Owners and Surveyors (November 2026)
Building defect claims are rarely lost on the technical merits alone. They are lost on dates: when the product was delivered, when the defect was known and when the claim form was issued. Loughton Contracts Plc v The Amtico Company Limited (2026) EWHC 2814 (TCC), handed down by Mr Justice
New Build Snagging Survey Lessons as New Homes Ombudsman Complaints Triple: What Wimbledon Buyers Should Know (November 2026)
{"content":[]} Complaints to the New Homes Ombudsman Service rose from 593 to 1,802 in a single year, and defects and snagging were the main issues raised [1][2]. For buyers in Wimbledon and across Merton, those figures make a strong case for an independent new build snagging survey, and for a
Phoenix Community Housing v Winch (2026) EWCC 69: County Court Refuses a Forced-Entry Order for Damp and Mould Works, What It Means for Disrepair Inspections and Surveyor Access in Wimbledon and South London (November 2026)
A tenant reports damp and mould throughout her flat, and then does not let the landlord's contractors in. The landlord asks the court for two things: an order that she give access, and permission to send a locksmith if she does not. On 16 November 2026 the County Court at
Awaab’s Law, Private Landlords and Expert Evidence: Who May Investigate a Hazard and What It Means for Wimbledon Disrepair Claims (November 2026)
Should a private landlord be allowed to decide for themselves who is competent to investigate damp, mould or another hazard, or should the law require a qualified person such as a building surveyor? That is Question 12 of the government's consultation on extending Awaab's Law to private rented homes, which