A lender advanced £12.9 million on the strength of a monitoring surveyor's report that put the cost to complete a development at about £2.9 million. The court found the realistic figure was closer to £5.4 million, and that the surveyor had previously priced the same project for the developer without properly disclosing it. Eiger Funding (PCC) Ltd v Ridge and Partners LLP (2026) EWHC 609 (TCC) ended in a £2.5 million award and is one of the most instructive surveyor negligence claim judgments of the year [1].
Key Takeaways
- The Technology and Construction Court awarded the lender £2.5 million in damages against its independent monitoring surveyor.
- The surveyor should have warned of a significant risk that costs would be substantially higher than the developer's figures.
- The firm had earlier prepared cost appraisals for the developer and told the lender's adviser there was "no conflict of interest".
- The building surveyor and quantity surveyor called as experts reached similar conclusions on what a competent monitoring surveyor would have advised.
- Defences on causation, reliance and contributory negligence all failed.
The facts
Eiger, a Guernsey lender, agreed in November 2018 to lend £12.9 million to a developer to complete the conversion of a building at 60 Old Hall Street, Liverpool, into about 122 flats with commercial space. The loan was introduced by a broker, North Wall Capital. The property had been valued in its uncompleted state at £13 million, with a gross development value of £20,654,678 [1].
Ridge acted as Independent Monitoring Surveyor, the professional a lender relies on to report on project cost, progress and risk. On 9 November 2018 it issued the report at the centre of the claim, known as Report 16. The loan agreement was signed on 30 November 2018, and a satisfactory initial report from a monitoring surveyor was a condition of the lending.
The project was meant to complete in the first half of 2019. The developer made negligible progress, and on 16 April 2020 the relevant companies went into administration. Eiger sued for part of its loss. Judgment was given on 16 March 2026 by Mr Adrian Williamson KC, sitting as a Deputy Judge of the High Court.
Breach one: the cost advice
The developer's figures suggested that about £3,060,000 remained to be spent. Report 16 gave several numbers, which the judge described as "somewhat baffling", but he read it as advising a cost to complete of around £2.9 million.
On what Ridge should have done, the judge found the expert evidence "helpful and, ultimately, leading to similar conclusions". Eiger called a building surveyor, Mr Stephen Turnham. Ridge called a quantity surveyor, Mr Kevin Whitehead. Both were described as highly experienced, measured and sensible [1].
The conclusion was that, given the inadequate costing information supplied by the developer, a reasonably competent monitoring surveyor would have advised that there was a significant risk of substantial costs over and above the developer's figures, both for the project as a whole and for the works left to complete. Ridge did not give that advice.
Breach two: the conflict of interest
Ridge had acted for the developer in 2015, preparing the cost appraisals that became the basis of a fixed price of £10.2 million in the building contract. In 2018 it was advising the lender on whether that price was reliable.
The judge referred to two RICS documents: the guidance for a lender's independent monitoring surveyor, which says the primary duty to the lender "must be beyond doubt", and the RICS professional statement on conflicts of interest, with its strict procedure for obtaining informed consent [2].
The findings were direct:
- Ridge had told the broker in terms that there was "no conflict of interest".
- It did not obtain informed consent as RICS defines it, and accepted by the end of the trial that it might well have failed to comply with the letter of the guidance.
- It did not mention that the £10.2 million figure was its own, arrived at in 2015, since when construction costs had risen by about 20%.
The judge held that Eiger had made out a real and potentially causative breach on the conflict issue.
A monitoring surveyor checking a price that the same firm produced for the developer three years earlier is in a clear conflict, and silence about it is not an option.
The defences that failed
Duty. Ridge at first denied owing any duty to Eiger. On the eve of closing submissions it conceded that it owed a duty to exercise reasonable skill and care in connection with the report.
Causation. Ridge argued that Report 16 was not mentioned in the lender's board papers or minutes. The judge rejected this. The broker had pressed hard for clarity on the cost to complete, and the report supplied "the final piece of the jigsaw". The lender did not commit until the loan agreement, which itself required a satisfactory monitoring report.
Reliance and contributory negligence. The judge found that Ridge had raised no matters of substance under these headings.
How the £2.5 million was calculated
| Item | Figure |
|---|---|
| Developer's stated cost to complete | £3,060,000 |
| Likely market price of the remaining works, 77% higher | £5,416,200 |
| Cost to complete as advised in Report 16 | about £2.9 million |
| Loss, after rounding | £2.5 million |
The judge accepted the building surveyor's evidence on realistic net construction costs and noted that the resulting project figure was in line with BCIS data. The loss was the difference between the cost risk the lender actually took on and the cost it had been told to expect.
Expert evidence in a surveyor negligence claim
The standard of a reasonably competent professional is proved by expert evidence from the same field. Here the two liability experts came from different surveying disciplines, yet their evidence converged, and that convergence settled the question of breach. Two points follow.
First, an expert who gives measured evidence, and concedes what ought to be conceded, is far more useful to the court than one who defends every point. Second, published benchmarks matter. The judge tested the figures against BCIS data, a check that any surveyor reporting on costs could have made at the time.
Lessons for Wimbledon lenders, developers and surveyors
South-west London has a steady flow of small and medium residential schemes funded by development finance, and the same roles appear on each: valuer, quantity surveyor, monitoring surveyor.
- Declare prior involvement in writing. If a firm has acted for the borrower on the same project, the lender must be told and give informed consent before the appointment.
- Say when information is inadequate. A report should state plainly that the developer's costings cannot be verified and what risk follows.
- Benchmark the numbers. Compare the developer's price with independent cost data and explain any gap.
- Give one clear figure. A report offering several inconsistent totals helps nobody.
- Lenders should ask the conflict question directly and keep the answer on file.
- Take early expert advice if a scheme fails. Liability turns on what a competent surveyor would have said at the time.
Frequently Asked Questions
What is an independent monitoring surveyor?
A surveyor appointed by a lender to report on a development's costs, programme and risks before and during the loan.
How much did the surveyor have to pay?
The court awarded damages of £2.5 million [1].
Is breaching RICS guidance the same as negligence?
Not automatically, but the court used the RICS guidance to identify what a competent surveyor should have done about the conflict.
Does a lender have to prove it relied on the report?
Yes. Here the court found reliance because a satisfactory report was a condition of the loan and the broker had pressed for the cost figures.
Conclusion
Eiger v Ridge turns on two ordinary professional duties: give a realistic warning about cost risk, and disclose a conflict properly. Lenders in Wimbledon and across London should check their monitoring surveyor's independence at the outset, and surveyors should treat the RICS conflict rules as a working checklist. This article is general information based on the published judgment and is not legal advice.