Thirsk v Berkeley Homes (2026) EWHC 215 (TCC): A £1.2m Flat Defects Claim, a Developer’s Costs Budget Cut Back and £140,000 Allowed for Experts, Lessons for Wimbledon Flat Owners and Surveyors (November 2026)

The owners of one London flat are claiming about £1.2m for alleged defects. Their own legal budget to trial has been agreed at more than £1.15m. The developer wanted to spend far more, and the High Court has said no. For anyone in Wimbledon weighing up a building defect claim, this short judgment shows what such a case costs to run, and how firmly the court now controls spending on experts [1].

Key Takeaways

  • This is a ruling on costs budgets only. Nothing has been decided about whether the flat is defective or who is liable.
  • The claim is put at £1,201,141.25, or £954,597 in the alternative, excluding VAT.
  • The judge found the developer's overall budget disproportionate on its face.
  • For the expert reports phase, the court allowed £140,000 for experts' fees and £220,000 in total, against £276,625 sought.

What the Case Is About

The claimants own a flat in Finsbury Park, north London. The defendants are two Berkeley Homes companies. They carried out work for or in connection with the flat: the original construction in 2012, and remediation works in 2014 to 2015.

The claimants say the works were carried out in breach of contract, in breach of the duty under the Defective Premises Act 1972, and negligently, so that the flat has defects. These are allegations awaiting an eight-day trial.

The sum claimed was first £858,263.56 excluding VAT. It rose after a Scott Schedule was served.

The judgment was handed down on 5 February 2026 by Mr Roger ter Haar KC, sitting as a Deputy High Court Judge in the Technology and Construction Court. He decided it on paper, after a case management conference in October 2025 [1].

Why the Costs Budget Mattered in This Building Defect Claim

In most multi-track cases, each side files a budget of the legal costs it expects to incur. The court approves or revises it. A party that wins will usually recover no more than its approved budget for each phase.

The court does not carry out a line-by-line assessment in advance. It asks whether the budgeted figure for each phase falls within the range of reasonable and proportionate costs.

Here the claimants' budget was agreed at £1,157,107.19. The developer's budget was not agreed. It had been increased by over £500,000, partly to allow for leading counsel. The judge had no doubt the overall amount was, on its face, disproportionate.

The Expert Evidence Phase

The largest point of interest for surveyors is the expert reports phase.

Item Developer sought Court allowed
Experts' fees Part of £276,625 £140,000
Solicitors' fees £75,625 £60,000
Counsel £61,000 £20,000
Phase total (estimated) £276,625 £220,000

The developer had already incurred £83,832.70 on this phase. Its total would have been £360,457.70. The claimants' equivalent total was £225,172.35.

The judge said that, given the significant sums already spent on experts, the overall figures could not be justified. A large part of the difference between the sides was the cost of involving counsel in the expert phase.

The pre-trial review phase was also cut, from £88,450 sought to £60,000.

Expert evidence is the engine of a defects claim. The court will pay for the engine, but not for a second one.

What This Means for Wimbledon Flat Owners

Flat owners in Wimbledon, Raynes Park and Colliers Wood who suspect defects in a new or recently converted home can take several points from the case.

  1. Costs can match the claim. A claim of about £1.2m is being run on budgets of more than £1.1m a side. Proportionality has to be considered from the first letter.
  2. Get independent evidence early. A building surveyor's inspection report, prepared before proceedings, helps to define what is wrong and whether a claim is worth bringing.
  3. A Scott Schedule shapes the case. It lists each alleged defect, the remedy and the cost. Here the claim value rose once it was served, so accuracy matters.
  4. There may be more than one legal route. Contract, the Defective Premises Act 1972 and negligence were all pleaded.
  5. Settlement deserves real thought. With budgets at this level, both sides have strong reasons to resolve matters before trial.

Lessons for Surveyors Acting as Expert Witnesses

  • Keep the scope of the report tied to the pleaded defects. Wide-ranging investigations may not be recoverable.
  • Give fee estimates that can be defended as proportionate to the sums in dispute.
  • Expect the court to compare one side's expert costs with the other's.
  • Work efficiently with the legal team. Heavy counsel involvement in the expert phase was a main reason the developer's figure was reduced.

Frequently Asked Questions

Has the court found the flat defective?
No. The judgment deals only with costs budgets. Liability will be decided at trial.

What is a costs budget?
A forecast of each side's legal costs by phase, which the court approves or revises under the Civil Procedure Rules.

How much can be spent on experts?
There is no fixed limit. The test is what is reasonable and proportionate. In this case £140,000 was allowed for the developer's future expert fees.

Does this apply to smaller claims?
The proportionality principle applies to every building defect claim, whatever its size.

Conclusion

Thirsk v Berkeley Homes shows the real cost of litigating defects in a single flat, and the court's readiness to trim expert and legal spending. Wimbledon owners considering a building defect claim should start with a focused independent survey and clear advice on proportionality. This article is general information only and is not legal advice.