Leaseholders of a West London block were sent advance demands of £1,487,349.48 for major works. The Upper Tribunal has now ruled that none of it is payable, because the landlord could not show what the works would be. This service charge major works dispute is one of the clearest recent examples of a poor specification sinking a demand.
Albemarle Ealing No.1 Limited v Fahim and other leaseholders (2026) UKUT 408 (LC) was decided by Upper Tribunal Judge Elizabeth Cooke on 23 October 2026, after a hearing on 29 September 2026 [1]. The building is in Ealing, not Wimbledon. But the lessons apply to every block of flats in Wimbledon and South West London where major works are planned.
Key Takeaways
- The landlord demanded about £1.49m in advance for major works at a block of 47 flats.
- The First-tier Tribunal called the specification 'woefully inadequate' but did not decide what was payable.
- The Upper Tribunal decided the point itself: the advance charges were not reasonable in amount and are not payable.
- Only one sixth of the fire door charges is payable, because only six of 36 doors had been fitted.
- Only about a third of the lift charges is payable, because only about a third of the work had been done.
The Building and the Service Charge Dispute
The property is Greystoke Court, Hanger Lane, London W5. It has three blocks and 47 flats. The leaseholders of 38 flats were respondents to the appeal.
The landlord bought the freehold in August 2023. It has planning permission to add 13 new flats on top of the blocks.
The case came to the Upper Tribunal on appeal from the First-tier Tribunal (Property Chamber). It covered four topics: major works, fire doors, lifts and insurance.
Why the Major Works Demand Failed
After a tender exercise, the contract was to go to a contractor on an estimate of £1,489,174.59. On 8 August 2024 the landlord sent advance service charge demands totalling £1,487,349.48.
The leaseholders called an expert witness. He said the specification was of a poor standard and left too much for the contractors to decide.
The First-tier Tribunal agreed that the specification was 'woefully inadequate'. But it then declined to decide what sum, if any, was payable.
The Upper Tribunal held that the First-tier Tribunal should have decided the question. So it made the decision itself.
The advance charges were not payable because they were not reasonable in amount. The landlord could not show what the works would be, let alone that their cost was reasonable.
That decision was made under sections 19(2) and 27A of the Landlord and Tenant Act 1985. The Upper Tribunal referred to Jarowicki v Freehold Managers (Nominees) Ltd (2016) UKUT 435 (LC) [1].
The point is a simple one. A landlord who asks for money in advance must be able to show what the money is for. If the specification is too vague to price, the tribunal cannot test whether the cost is reasonable.
Fire Doors and Lifts: Pay Only for What Has Been Done
The same idea ran through the rest of the decision.
| Item | What was charged | What had been done | What is payable |
|---|---|---|---|
| Fire doors | About £146,500 over two years | Six of 36 doors fitted by the First-tier Tribunal hearing | One sixth, £24,426 |
| Block 1 lift work (first charge) | £102,660 | About a third | £34,220 |
| Block 1 lift work (second charge) | £60,884 | About a third | £20,295 |
| "Emergency" lift charge | £30,384 | Not shown to be reasonably incurred | Nil |
The fire doors were needed after an enforcement notice in August 2021. The finding on the lifts rested on the evidence of the landlord's own lift engineer.
The Insurance Point
The landlord did win one issue. The First-tier Tribunal had made a deduction from the 2021-22 insurance premium because the landlord paid by instalments. It did so on its own initiative and without explaining the figure.
The Upper Tribunal set that deduction aside. The premium is payable in full. A tribunal should not cut a charge without evidence and reasons.
A separate appeal about dispensation from the consultation requirements, under section 20ZA, is still pending.
What It Means for Leaseholders and Landlords
For flat owners
- Ask to see the specification. A demand for a large advance payment should be backed by a document that says clearly what work will be done.
- Check what has been completed. If you have been charged for 36 fire doors, count the doors.
- Keep records. Dated photographs and notes of works done, or not done, are powerful evidence.
- Consultation is not the whole answer. A section 20 consultation does not cure a specification that is too vague to price.
For landlords and managing agents
- Invest in the specification first. Tendering on a thin document invites wide price ranges, variations and challenge.
- Charge in step with progress. Billing for work that has not been done will not survive scrutiny.
- Be ready to prove each cost. Labels such as "emergency" need evidence behind them.
The Role of Surveyors and Expert Evidence in a Major Works Dispute
This was, at heart, a dispute about a surveying document. The decision does not name the leaseholders' expert witness or state his profession. But his evidence about the quality of the specification was central.
Three practical points follow for surveyors.
A condition survey comes first. Before any specification is written, a chartered building surveyor should inspect the building and record its defects. The specification should flow from that survey.
The specification must be capable of being priced. It should describe the work, the materials and the standards in enough detail that different contractors are pricing the same thing. Where it leaves the scope to the contractor, tenders cannot be compared and costs cannot be tested.
Independent review has real value. Leaseholders faced with a large demand can ask a building surveyor to review the landlord's specification. If the matter goes to the tribunal, that surveyor may act as an expert witness.
An expert witness in the tribunal owes a duty to the tribunal, not to the party who pays. The report should be balanced. It should say what is wrong with a specification and also what is sound.
What Wimbledon Flat Owners Should Do Now
Many blocks in Wimbledon and across South West London face major works, from roof renewals to fire safety upgrades. If a demand arrives:
- Ask for the condition survey, the specification and the tender report.
- Check whether the work described matches what the building needs.
- Compare any charges for past work with what has in fact been completed.
- Take early advice from a chartered building surveyor.
- Raise concerns in writing during the consultation period.
Frequently Asked Questions
Can a landlord demand service charges in advance for major works?
Often yes, if the lease allows it. But under section 19(2) of the Landlord and Tenant Act 1985, an advance charge must be no more than is reasonable.
Why was the £1.49m not payable?
The landlord could not show what the works would be. Without that, it could not show that the cost was reasonable.
Do I have to pay for works that have not been done?
In this case, leaseholders were liable only for the share of the fire door and lift work that had been carried out.
Does a section 20 consultation make the charge valid?
No. Consultation is a separate requirement. It does not make an unreasonable amount reasonable.
Should leaseholders instruct their own surveyor?
Where large sums are at stake, an independent review by a building surveyor can show whether a specification and its cost stand up.
Conclusion
Albemarle Ealing v Fahim is a reminder that a service charge for major works is only as strong as the specification behind it. A £1.49m demand fell away because nobody could say exactly what it would buy. And charges for fire doors and lift work were cut back to match what had been done.
For Wimbledon flat owners and their managing agents, the next step is clear. Get the building surveyed and the works properly specified before the first demand goes out, and ask for independent advice as soon as doubts arise.
References
- Albemarle Ealing No.1 Limited v Fahim and others (2026) UKUT 408 (LC), Upper Tribunal (Lands Chamber), decision of 23 October 2026, published by The National Archives. caselaw.nationalarchives.gov.uk.